Six buildings rising together on the waterfront.
Six buildings, one constrained site.
Six buildings are being built at once on a waterfront site in Khorfakkan, with structure, facade and MEP progressing together. Coordination issues surfaced as soon as the structure rose: a podium beam crossing smoke-shaft openings, retail curtain walls across service routes, and a fresh-air design that changed in all six buildings.
Coordinate early, protect what is installed.
We raise each clash through a formal RFI with a proposed solution before it reaches site, protect installed drainage and puddle flanges during the structural works, and have proposed a project-wide revision of the fresh-air design, submitted as a variation.
Below ground, keeping pace with the structure.
By November 2026 the underground drainage and cast-in sleeves were following the raft and podium pours building by building, and 111 of 138 work inspections had been approved. The engineering submittals for the main MEP packages are under review, for a programme that completes the six buildings between October 2027 and March 2028.