Two towers, inspected floor by floor.
A high-rise on a fixed programme.
Two towers over a four-level podium, about 500 apartments, and MEP installation running floor by floor behind the structure and the facade, while the ground-floor lobby was redesigned during execution.
Inspect everything, track every delivery.
Every activity is inspected before it is closed up: by mid-November 2026 more than 1,500 work inspection requests had been raised across the electrical, plumbing, mechanical and ceiling-closure works.
Long-lead equipment is tracked from approval to factory test and delivery – FAHUs, BTU meters, heat exchangers, fan-coil units, LV panels, busbar and the standby generator – and extra draughting capacity keeps shop drawings ahead of site.
Second fix to floor 30.
By November 2026 second fix had reached floor 30 of the main tower and ceilings were closing up to floor 36. The fresh-air units, BTU meters, heat exchangers and fan-coil units were on site, the first LV panel had been delivered with its factory acceptance test scheduled, and the standby generator was ready for delivery.