ISO 9001 · ISO 14001 · ISO 45001 certified  |  Licensed in Dubai, Sharjah and Abu Dhabi
Asian Falcons Engineering Contracting L.L.C. Tender enquiry
Home/Projects/Sky Hills Residences 3
Case study · Residential · In progress · 2025–2027

Sky Hills Residences 3

MEP for a 42-storey residential tower and its 10-storey companion in Jumeirah Village Circle: about 500 apartments on district cooling, 773 fan-coil units and 4,700 kW of connected load.

Sky Hills Residences 3
Sky Hills Residences 3 – Jumeirah Village Circle, Dubai
Project overview

Our largest high-rise package to date: MEP for a 42-storey residential tower and a 10-storey companion tower over a four-level podium (LG+G+4P+42+R), with about 500 apartments – district cooling, 4,700 kW of connected load, home automation and temporary site services for the main contractor.

Status
In progress
Sector
Residential
Location
Jumeirah Village Circle, Dubai
Employer
HRE Real Estate Development
Main contractor
HRE Construction
Consultant
AREC Engineering Consultants
Building
LG+G+4P+42+R: a 42-storey tower and a 10-storey tower over a shared podium; about 500 apartments and 12 shops
Start on site
February 2025
Our scope
HVAC, electrical, ELV, plumbing, LPG and site logistics
42storeys
Main tower above the podium
1,361TR
District cooling through two ETS
773FCUs
Chilled-water fan-coil units
4,700kW
Connected electrical load
1,500+WIRs
Work inspections raised by November 2026
3FAHUs
Fresh-air handling units
Challenge, solution, outcome

Two towers, inspected floor by floor.

01 / The challenge

A high-rise on a fixed programme.

Two towers over a four-level podium, about 500 apartments, and MEP installation running floor by floor behind the structure and the facade, while the ground-floor lobby was redesigned during execution.

02 / Our solution

Inspect everything, track every delivery.

Every activity is inspected before it is closed up: by mid-November 2026 more than 1,500 work inspection requests had been raised across the electrical, plumbing, mechanical and ceiling-closure works.

Long-lead equipment is tracked from approval to factory test and delivery – FAHUs, BTU meters, heat exchangers, fan-coil units, LV panels, busbar and the standby generator – and extra draughting capacity keeps shop drawings ahead of site.

03 / The outcome

Second fix to floor 30.

By November 2026 second fix had reached floor 30 of the main tower and ceilings were closing up to floor 36. The fresh-air units, BTU meters, heat exchangers and fan-coil units were on site, the first LV panel had been delivered with its factory acceptance test scheduled, and the standby generator was ready for delivery.

Systems in our scope

What we are engineering and installing.

Engineered, supplied, installed, tested and commissioned by Asian Falcons. Fire fighting and fire alarm are installed by a specialist; we coordinate them and provide their containment.

HVAC

  • District cooling through two energy transfer stations
  • Plate heat exchangers and CHW pumps
  • 773 chilled-water fan-coil units
  • Three fresh-air handling units
  • Ventilation and smoke fans
  • BTU metering for every apartment

Electrical

  • 4,700 kW connected load
  • Three 1,500 kVA DEWA transformers
  • LV switchgear and busbar risers
  • Standby generator with ATS panels
  • Lighting, emergency and aviation lights

ELV & controls

  • Building management system
  • Home automation
  • ELV systems

Plumbing & LPG

  • Drainage and water supply
  • Transfer, booster and sump pump sets
  • GRP water tanks
  • Central LPG system

Site logistics

  • Temporary site services for the main contractor
  • Landscape MEP
Timeline

Key dates.

  • Jan 2025MEP subcontract signed with HRE Construction
  • Feb 2025First work inspection on site
  • Jun 2026Fresh-air handling units delivered
  • Jul 2026BTU meters delivered
  • Nov 2026First LV panel delivered; factory acceptance test scheduled
  • Nov 2026Standby generator ready for delivery; first busbar batch due
Approvals and inspections

Inspected and approved at every stage.

  • More than 1,250 work inspections approved by AREC Engineering Consultants by November 2026
  • 150 of 165 material inspections approved
  • 58 material submittals and 56 shop drawings approved as noted by the consultant
Work with us

Planning a similar project?

Send us your tender documents, drawings and BOQs. Our pre-construction team returns a priced offer with a tender programme and technical submission.