Re-engineered mid-way, finished without delay.
A design change after the mock-up.
In September 2024, after the mock-up apartment had been approved, the design changed: square diffusers became linear slot diffusers, grilles became continuous linear bar grilles in every flat, and standard thermostats were replaced by home-automation thermostats – changing wall openings across the tower.
Re-detail, re-sequence, hold suppliers to dates.
We notified the change formally, re-detailed the air distribution and controls, and re-sequenced the works floor by floor with the main contractor.
When the home-automation thermostats ran late, we set and enforced a firm delivery date with the supplier so that installation could continue to programme.
Completed with no delays or penalties.
The tower was completed in April 2026. The main contractor confirmed in writing that the project was completed satisfactorily and in full accordance with the project requirements and specifications, and that no delays or penalties were applied.