Case study · Residential · Completed · 2023–2026

Marsa Dubai Residential Tower

MEP for a 20-storey residential tower in Dubai Marina, from the rooftop chillers to the apartment thermostats – completed in April 2026 with no delays or penalties.

Marsa Dubai Residential Tower
Marsa Dubai Residential Tower – Marsa Dubai (Dubai Marina) · Visualisation
Project overview

Full MEP for a 20-storey residential tower: air-cooled chillers and FAHUs, fire-rated ductwork and smoke management, busbar trunking, pumps and BMS.

Status
Completed
Sector
Residential
Location
Marsa Dubai (Dubai Marina)
Employer
Continental Investments
Main contractor
Structure Advanced Building Contracting
Consultant
Lacasa Architects & Engineering
Building
G+2P+20+R residential tower
Start on site
February 2024
Completion
April 2026
Our scope
Full MEP, BMS
20storeys
Residential floors over a two-level podium
3chillers
Air-cooled, on the roof
2FAHUs
With heat-recovery wheels
Challenge, solution, outcome

Re-engineered mid-way, finished without delay.

01 / The challenge

A design change after the mock-up.

In September 2024, after the mock-up apartment had been approved, the design changed: square diffusers became linear slot diffusers, grilles became continuous linear bar grilles in every flat, and standard thermostats were replaced by home-automation thermostats – changing wall openings across the tower.

02 / Our solution

Re-detail, re-sequence, hold suppliers to dates.

We notified the change formally, re-detailed the air distribution and controls, and re-sequenced the works floor by floor with the main contractor.

When the home-automation thermostats ran late, we set and enforced a firm delivery date with the supplier so that installation could continue to programme.

03 / The outcome

Completed with no delays or penalties.

The tower was completed in April 2026. The main contractor confirmed in writing that the project was completed satisfactorily and in full accordance with the project requirements and specifications, and that no delays or penalties were applied.

Systems delivered

What we engineered and installed.

Every system below was engineered, supplied, installed, tested and commissioned by Asian Falcons or by approved specialists under our supervision.

Central plant

  • Three air-cooled chillers
  • Four chilled-water primary pump sets
  • Pressurisation and chemical dosing
  • BTU metering for billing

Air distribution

  • Two FAHUs with heat-recovery wheels
  • Fan-coil units on every floor
  • Linear slot diffusers and bar grilles
  • GI, phenolic and fire-rated ductwork

Life safety

  • Stair pressurisation and smoke extract fans
  • Civil Defence inspection of smoke management
  • Fire pump set

Controls & power

  • Building management system
  • Home-automation thermostats
  • Busbar trunking
Timeline

Key dates.

  • Oct 2023Approved as subcontractor by Lacasa Architects & Engineering
  • Feb 2024Subcontract signed with Structure Advanced Building Contracting
  • Mar 2024Chillers ordered
  • Sep 2024Design change notified: linear diffusers and home-automation thermostats
  • Aug 2025Fire-rated ductwork certified for Civil Defence
  • Apr 2026Project completed – no delays or penalties
The contractor demonstrated strong technical capability, effective coordination, and commitment to successful project completion.
Structure Advanced Building Contracting · Reference letter, April 2026