Case study · Residential · Completed · 2022–2023

Donna Twin Towers

Completing two stalled 30-storey towers in Dubai Silicon Oasis: full MEP for almost 400 units, with 2,400 TR of chillers and 12,100 kW of connected load.

Donna Twin Towers
Donna Twin Towers – Dubai Silicon Oasis
Project overview

2B+G+3P+30 twin towers: eight air-cooled chillers, four FAHUs, ten CHW pumps, smoke management, 12,100 kW connected load over eleven LV panels, generator, ELV and plumbing.

Status
Completed
Sector
Residential
Location
Dubai Silicon Oasis
Employer
Al Dhafra Property Management
Main contractor
Modern Building Contracting
Consultant
Arab Experts Engineering Consultants (AEX)
Building
2B+G+3P+30 twin towers on a shared podium, almost 400 units
Start on site
January 2022
Completion
2023
Our scope
Full MEP
2,400TR
Air-cooled chiller plant
12,100kW
Connected electrical load
8chillers
With ten chilled-water pumps
11LV panels
Low-voltage distribution
1,450units
Fan-coil and AC units
400units
Almost 400, in two towers
Challenge, solution, outcome

Finishing a building others had started.

01 / The challenge

A part-built tower pair.

Donna Twin Towers had stalled during construction. Our scope covered the new MEP works and the inspection, repair and, where needed, re-installation of services that had already been installed – to the standard the authorities would inspect at handover.

02 / Our solution

Survey, repair, complete.

We surveyed the existing installations, recorded what could be kept and repaired or replaced the rest before new work covered it, then completed the central plant, risers and apartment systems tower by tower.

Smoke management was engineered and tested to Dubai Civil Defence requirements, and the electrical distribution was completed over eleven LV panels with busbar risers and a standby generator.

03 / The outcome

Two towers completed.

Both towers were completed in 2023, with the systems tested and commissioned for handover to Dubai Silicon Oasis Authority, Civil Defence and DEWA.

Systems delivered

What we engineered and installed.

Every system below was engineered, supplied, installed, tested and commissioned by Asian Falcons or by approved specialists under our supervision.

HVAC

  • Eight air-cooled chillers, 2,400 TR
  • Ten chilled-water pumps
  • Four fresh-air handling units
  • About 1,450 fan-coil and AC units
  • Smoke management to Dubai Civil Defence
  • Kitchen ventilation

Electrical

  • 12,100 kW connected load
  • Eleven LV panels and busbar risers
  • Standby generator with ATS
  • Lighting and lightning protection

Plumbing

  • PPR water and uPVC drainage
  • Transfer and sump pump sets
  • GRP roof tanks

ELV & BMS

  • ELV systems
  • Building management system
Timeline

Key dates.

  • Jul 2021HVAC prequalification approved by Arab Experts Engineering Consultants
  • Jan 2022MEP subcontract signed with Modern Building Contracting
  • 2022Central plant, risers and BMS procured and installed
  • 2023Testing, commissioning and completion of both towers
Approvals and inspections

Inspected and approved at every stage.

  • Prequalification approved by Arab Experts Engineering Consultants (AEX), July 2021
  • Smoke management designed and tested to Dubai Civil Defence requirements
  • Systems commissioned for handover to DSOA, Civil Defence and DEWA