ISO 9001 · ISO 14001 · ISO 45001 certified  |  Licensed in Dubai, Sharjah and Abu Dhabi
Asian Falcons Engineering Contracting L.L.C. Tender enquiry
Visualisation
Home/Projects/Commercial & Robotic Car Park
Case study · Transport & Infrastructure · In progress · 2024–2026

Commercial & Robotic Car Park

Full MEP and ELV – engineered, supplied, installed and commissioned – for an RTA smart-parking project in Souq Al Kabeer: an automated car park with six robotic towers, 352 spaces and commercial areas.

Commercial & Robotic Car Park
Commercial & Robotic Car Park – Souq Al Kabeer, Dubai · Visualisation
Project overview

Full MEP for an RTA smart-parking project: an automated car park for 352 cars with six robotic parking towers over a basement, ground and six floors, with commercial areas and a built-up area of 17,500 m².

Status
In progress
Sector
Transport & Infrastructure
Location
Souq Al Kabeer, Dubai
Employer
Wahat Al Bastakiya (RTA smart project)
Main contractor
ORC Contracting
Consultant
Al Shandagha Architects & Engineering Consultants
Building
1B+G+6+R commercial building and automated car park with six robotic parking towers, 17,500 m²
Start on site
November 2024
Our scope
Full MEP, interfaces with robotic parking
352cars
Automated parking capacity
6towers
Robotic parking towers served
2,143kW
Connected electrical load
825kVA
Standby generator
637heads
Sprinkler heads
96%
Electrical and plumbing inspections approved first time
Challenge, solution, outcome

Building services for a car park run by robots.

01 / The challenge

A building that is also a machine.

The MEP had to serve six robotic parking towers and their control rooms, meet Civil Defence rules for car-park smoke management and fire suppression, and adapt to a DEWA-approved electrical design that moved the substation from the basement to the ground floor.

02 / Our solution

Engineer the interfaces, then build.

We worked through each interface with the consultant and the robotics supplier: FM-200 clean-agent protection for the robotics control-panel room, as Civil Defence rules require, and a fire strategy for the robotic towers based on the supplier's confirmation that they contain no hydraulic parts.

The smoke management system was redesigned to the Civil Defence approval, the generator was increased from 500 to 825 kVA, and two ACB panels were added for the relocated substation. When the specified insulation was unavailable, an approved equivalent kept the ceiling-closure target.

03 / The outcome

Authority approvals secured.

Civil Defence gave final approval of the smoke management system in September 2025, and DEWA approved the load schedule in December 2025. 392 of 407 electrical and plumbing work inspections (96%) and 239 of 262 material inspections (91%) were approved first time. In November 2026 the project was in close-out, with DEWA energisation of the substation under way.

Systems in our scope

What we are engineering and installing.

The systems below are in our scope: engineered, supplied, installed, tested and commissioned by Asian Falcons or by approved specialists under our supervision.

Power

  • DEWA substation with 1,000 kVA and 1,500 kVA transformers
  • Two ACB panels, 2,400 A and 1,600 A
  • 825 kVA generator with ATS
  • 1,090 light fittings, 313 emergency lights and 84 exit signs
  • EV charging points

Life safety

  • 33 smoke exhaust fans, approved by Civil Defence
  • 637 sprinkler heads
  • Combined fire pump set, 1,250 US gpm
  • FM-200 for the robotics control room
  • Addressable fire alarm

HVAC & plumbing

  • DX fan-coil units for commercial areas and control rooms
  • Ventilation and extract
  • Water supply, drainage and sump pumps

ELV

  • Structured cabling, CCTV and access control
  • Interfaces with the robotic parking system
Timeline

Key dates.

  • 1 Oct 2024Approved by the client as MEP subcontractor, through Al Shandagha
  • 12 Oct 2024Letter of award from ORC Contracting
  • Nov 2024Embedded conduits and sleeves on the first slabs
  • Sep 2025Civil Defence final approval of the smoke management system
  • Dec 2025DEWA load schedule approved
  • Jun–Oct 2026Close-out documents submitted
Approvals and inspections

Inspected and approved at every stage.

  • Approved as MEP subcontractor through Al Shandagha Architects & Engineering Consultants, October 2024
  • Smoke management system: final approval by Dubai Civil Defence, September 2025
  • Load schedule approved by DEWA, December 2025
  • 96% of electrical and plumbing work inspections and 91% of material inspections approved first time
Work with us

Planning a similar project?

Send us your tender documents, drawings and BOQs. Our pre-construction team returns a priced offer with a tender programme and technical submission.