Building services for a car park run by robots.
A building that is also a machine.
The MEP had to serve six robotic parking towers and their control rooms, meet Civil Defence rules for car-park smoke management and fire suppression, and adapt to a DEWA-approved electrical design that moved the substation from the basement to the ground floor.
Engineer the interfaces, then build.
We worked through each interface with the consultant and the robotics supplier: FM-200 clean-agent protection for the robotics control-panel room, as Civil Defence rules require, and a fire strategy for the robotic towers based on the supplier's confirmation that they contain no hydraulic parts.
The smoke management system was redesigned to the Civil Defence approval, the generator was increased from 500 to 825 kVA, and two ACB panels were added for the relocated substation. When the specified insulation was unavailable, an approved equivalent kept the ceiling-closure target.
Authority approvals secured.
Civil Defence gave final approval of the smoke management system in September 2025, and DEWA approved the load schedule in December 2025. 392 of 407 electrical and plumbing work inspections (96%) and 239 of 262 material inspections (91%) were approved first time. In November 2026 the project was in close-out, with DEWA energisation of the substation under way.