Design to handover in sixty days.
Sixty days, everything included.
The client needed a flagship Wolfi's and Colnago bike showroom on Hudayriat Island ready in 60 days – MEP design, authority approvals, procurement, installation and testing included – on an island site with no existing services.
Design, approve and buy in parallel.
As design and build MEP subcontractor to Arena Middle East & Asia, we designed the MEP and ordered long-lead equipment – the fire pump set and its pump room among the first orders – while approvals were in progress, and built the back-of-house infrastructure (tanks, pump room, manholes and trenches) alongside the steel structure.
Each system was tested as it was completed, so the authority inspections could follow straight on.
Designed, built and approved in 60 days.
The MEP and back-of-house infrastructure were designed, built and approved within 60 days, with a 500 kW supply approved by the Abu Dhabi Distribution Company and fire systems approved by Abu Dhabi Civil Defence.